Architect: McKee & Associates
Contract Amount: $ 10,898,300.00
Project Manager- Max White
Construction began in November of 2022 and and is anticipated to be complete by the end of summer 2024.
Architect: McKee & Associates
Contract Amount: $ 10,898,300.00
Project Manager- Max White
Construction began in November of 2022 and and is anticipated to be complete by the end of summer 2024.
Architect: McKee & Associates
Contract Amount: $ 13,888,900.00
Project Manager- Tim Adams
Construction began in July of 2022 and and is anticipated to be complete by the end of 2024.
Architect: McKee & Associates
Contract Amount: $ 7,153,600.00
Project Manager- Tim Adams
Superintendent- Stan Shaw
Construction began in May of 2022 and and is anticipated to be complete by the end of 2023.
Architect: Lathan Associates
Contract Amount: $ 24,142,700.00
Project Manager- Wayne Watford
Superintendent- Cheney Fox
Construction began in April of 2022 and and is anticipated to be complete by the end of 2024.
Architect: Chambless King
Contract Amount: $ 7,975,949.00
Project Manager- Max White
Superintendent- Eli Blackmon
Construction began in April of 2022 and and is anticipated to be complete by the end of summer 2023.
Architect: McKee & Associates
Contract Amount: $4,398,900.00
Project Manager- Tim Adams
Superintendent- Mike Ross
Construction began in February of 2022 and and is anticipated to be complete by the end of summer 2023.
Architect: Ward Scott Architecture, Inc.
Contract Amount: $30,435,765.00
Project Manager- Wayne Watford
Superintendent- Randy Jones
Construction will begin in June of 2021 and and is anticipated to be complete by the end of 2022.
Architect: Goodwyn | Mills | Cawood
Contract Amount: $20,786,500.00
Project Manager- Max White
Superintendent- Wade Peterson
Construction is anticipated to begin in December 2020 and and is anticipated to be complete by the summer 2022.