Architect: McKee & Associates
Contract Amount: $ 13,888,900.00
Project Manager- Tim Adams
Construction began in July of 2022 and and is anticipated to be complete in 2025.
Architect: McKee & Associates
Contract Amount: $ 13,888,900.00
Project Manager- Tim Adams
Construction began in July of 2022 and and is anticipated to be complete in 2025.
Architect: McKee & Associates
Contract Amount: $ 7,153,600.00
Project Manager- Tim Adams
Superintendent- Stan Shaw
Construction began in May of 2022 and and is anticipated to be complete by the end of 2023.
Architect: Lathan Associates
Contract Amount: $ 24,142,700.00
Project Manager- Wayne Watford
Superintendent- Jack Hanes
Construction began in April of 2022 and and is anticipated to be complete in 2025.




Architect: Chambless King
Contract Amount: $ 7,975,949.00
Project Manager- Max White
Superintendent- Eli Blackmon
Construction began in April of 2022 and was complete in September of 2023.
Architect: McKee & Associates
Contract Amount: $4,398,900.00
Project Manager- Tim Adams
Superintendent- Curtis Schultz
Construction began in February of 2022 and was completed in August of 2023.













Architect: Ward Scott Architecture, Inc.
Contract Amount: $30,435,765.00
Project Manager- Wayne Watford
Superintendent- Randy Jones
Construction began in June of 2021 and was complete in July of 2023.


Architect: Goodwyn | Mills | Cawood
Contract Amount: $20,786,500.00
Project Manager- Max White
Superintendent- Wade Peterson
Construction began in December 2020 and and was completed in July 2022.
Architect: Seay, Seay & Litchfield
Contract Amount: $8,506,200.00
Project Manager- Wayne Watford
Superintendent- Randy Jones
Construction began in October of 2020 and was completed in September of 2022.